MEADOW RIDGE RESORT
EGG HARBOR, WISCONSIN - DOOR COUNTY

| PROJECT SCOPE: |
ON 3/21/01, WIESER CONCRETE WAS CONTACTED BY BILL BAUDHUIN ABOUT A NEW POURED-IN-PLACE TANK THAT HAD COLLAPSED DUE TO THE SOIL LOAD. THE TANK HELD 65,000 GALLONS AND NEEDED TO BE REPLACED. WE PROPOSED USING PRECAST TANKS - FOR A TOTAL OF 66,000 GALLONS
• 3 - 18,000 HOLDING TANKS
• 1 - 12,000 HOLDING TANK
• THESE TANKS WERE USED BECAUSE:
• THEY WERE COMPETITIVELY PRICED,
• HAD ADEQUATE CAPACITY,
• COULD BE INSTALLED WITHIN THE TIMELINE (WANTED TANK REPLACED WITHIN 1 MONTH)
• STATE PRE-APPROVED
• PRE-ENGINEERED TO WITHSTAND LOADING CONDITION |
| PRODUCT PRODUCTION REQUIREMENTS: |
• ALL TANKS HOOKED TOGETHER WITH CONNECTING PIPES ON BOTTOM SO THEY WOULD FILL AND EMPTY THROUGH ONE INLET (FILL) AND ONE PUMP-OUT PORT (EMPTY)
• PRODUCT WAS ORDERED 4/4/01 AND DELIVERED 4/17/01 |
| INSTALLATION TIMELINE: |
| • TANKS WERE DELIVERED, SET IN PLACE AND PIPES HOOKED UP IN 5 1/2 HOURS |
| OTHER:
|
ENGINEER:BAUDHUIN, INC. STURGEON BAY, WISCONSIN
CONTRACTOR:PARENT CONSTRUCTION, INC. BAILEYS HARBOR, WISCONSIN |
|