ROCHESTER HIGHWAY BARRIER INSTALLATION
ZUMBRO RIVER CONSTRUCTION
ROCHESTER, MINNESOTA
| PROJECT SCOPE: |
| • PRODUCE 71,200 FEET OF HIGHWAY BARRIER |
| PRODUCT PRODUCTION REQUIREMENTS: |
| • TO MEET INSTALLATION TIMEFRAME, 105 MEDIAN BARRIER WERE PRODUCED DAILY. |
| INSTALLATION TIMELINE: |
• ORDER RECEIVED FEBRUARY 5, 2003
• DELIVERY STARTED MAY 10, 2003 |
| OTHER:
|
• WIESER CONCRETE’S ABILITY TO DESIGN AND BUILD FORMS ALLOWS US TO INCREASE PRODUCTION CAPACITY AS REQUIRED FOR ANY PROJECT.
|
|