FORT WORTH GRAIN COMPANY
FORT WORTH, TEXAS

PROJECT SCOPE:

  • 2,618 LINEAL FOOT 16' BUNKER SILO

  • INSTALLATION IN TEXAS

PRODUCT PRODUCTION REQUIREMENTS:

  • 374 16' HIGH L PANEL, 7' LONG

INSTALLATION TIMELINE:

  • ORDER PLACED 5/23/00

  • PRODUCT STARTED LOADING 5/30/00

  • INSTALLATION WAS COMPLETED IN 6 DAYS

OTHER:

  • PANELS WERE TRANSPORTED ON 126 SEMI-TRAILERS



ENGE FARMS - BUNKERS & 
SLATTED FLOOR MANURE STORAGE SYSTEM
SAUK CITY, WISCONSIN

PROJECT SCOPE:

  • 700 COW SLATTED FLOOR MANURE STORAGE SYSTEM

  • SYSTEM INCLUDED BREEZEWAY, HOLDING AND SPECIAL NEEDS AREA

  • FIVE CELL BUNKER SILO - 12' HIGH

  • 6,500,000 GALLON STORAGE CAPACITY

PRODUCT PRODUCTION REQUIREMENTS:

  • 216 TRUCKLOADS OF PRODUCT

INSTALLATION TIMELINE:

  • FOUR WEEKS TO COMPLETE PROJECT

OTHER:

  • WIESER ENGINEERING WORKED TO SECURE WPDES & NRCS PERMITS



ANOKA HENNEPIN ELEMENTARY SCHOOL
ANDOVER, MINNESOTA

PROJECT SCOPE:

  • 1-15,000 GALLON SEPTIC TANK

  • 1-15,000 GALLON SEPTIC TANK (DUAL COMPARTMENT)

  • 1-12,000 GALLON SAND FILTER DOSING PUMP STATION

  • 1-12,000 GALLON DOSING STATION

PRODUCT PRODUCTION REQUIREMENTS:

  • TANKS AND ACCESSORIES WERE PRODUCED TO ENGINEERING SPECIFICATIONS

  • 4 DAY PRODUCT PRODUCTION

INSTALLATION TIMELINE:

  • TANKS WERE DELIVERED AND SET IN 1 DAY

ENGINEER:

  • NORTH AMERICAN WETLAND ENGINEERING

CONTRACTOR:

  • J.R. FERCHE, INC. - RICE, MINNESOTA



INTERSTATE 394 TWIN CELL BOX CULVERT
MINNEAPOLIS/ST. PAUL, MINNESOTA

PROJECT SCOPE:

  • 1232 LINEAL FEET TWIN CELL BOX CULVERT

PRODUCT PRODUCTION REQUIREMENTS:

  • 154 - 8' LONG SECTIONS WEIGHING 47,500LB/EACH

  • PRODUCTION TOOK 5 WEEKS WORKING 7 DAYS/WEEK

INSTALLATION TIMELINE:

  • INSTALLED CULVERT IN 4 DAYS

OTHER:

  • WIESER DESIGNED AND BUILT THE FORM TO PRODUCE THIS PRODUCT AS SPECIFIED BY DESIGN

 



FORT SNELLING NATIONAL CEMETERY
ST. PAUL, MINNESOTA

PROJECT SCOPE:

  • 10,500 double-depth single-cavity burial vaults

PRODUCT PRODUCTION REQUIREMENTS:

  • Production of the vaults began at the Maiden Rock facility on July 28th and will be completed by November 8th, 2003

  • To accomplish this timeline, it required that a quantity equal to 156 single-cavity vaults be produced each day.

INSTALLATION TIMELINE:

  • Installation to be completed November 8th, 2003

OTHER:

  • To accomplish this objective Wieser Engineering and Manufacturing, Inc., with Steel Services, Inc., designed a twin-cavity burial vault forming system.  This system enabled Wieser to efficiently produce two castings a day from each form.  Once designed, Wieser Concrete Products, Inc., secured approval from the Veteran’s Administration to use this product.

 